Administration - Dan Schluender, City Engineer
Title
Title
Receive Feasibility Report and Order Public Hearing for the Hidden Oaks Area Street Reconstructions, Improvement Project No. 22-06
end
Executive Summary
Council is asked to receive the feasibility report for the Hidden Oaks Area Street Reconstructions, Improvement Project No. 22-06 and order a public hearing.
Background
At the September 20, 2021 City Council meetiong, Council initiated the Hidden Oaks Street Reconstructions project and ordered the preparation of a feasiblity report. The Hidden Oaks Area Street Reconstruction project consists of reconstruction of the following streets:
• 97th Avenue from Hamline Avenue to Yalta Street
• 97th Lane from Hamline Avenue to Xebec Street
• 97th Court from West cul-de-sac to Hamline Avenue
• 98th Avenue from Hamline Avenue to Xebec Street
• 98th Lane from Wake Street to Yalta Street
• 99th Avenue from Wake Street to Xebec Street
• 99th Lane from Xebec Street to Austin Street
• Hamline Avenue from Edgewood Road to North cul-de-sac
• Wake Street from 98th Avenue to 99th Avenue
• Wake Court from 99th Avenue to North cul-de-sac
• Xebec Street from Edgewood Road to 99th Lane
• Yalta Street from 97th Avenue to 99th Lane
The project area consists of residential streets with concrete curb and gutter. The proposed improvements include full concrete curb and gutter removal and replacement, minor storm drainage improvements, spot water main repair, asphalt surface replacement, traffic control signage replacement, and appurtenant construction.
The estimated cost of these proposed improvements is $4,889,565.00 with $1,282,052.00 to be assessed to the benefitting properties over a 15-year period. Replacement of existing sanitary sewer castings/rings and replacement of malfunctioning water main gate valves and curb stops in certain locations at an estimated cost of $176,580.00 is proposed to be paid for by City Public Utility Funds. The remaining portion of $3,430,933 is proposed to be paid from the City’s Pavement Management Program Fund.
The proposed project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.
Schedule of Actions
09/20/2021 |
Initiate Project and Order Preparation of Feasibility Report |
12/20/2021 |
Receive Feasibility Report and Order Public Hearing |
01/05/2021 |
Public Information Meeting |
01/19/2022 |
Hold Public Hearing, Order Improvement, and Order |
|
Preparation of Plans and Specifications |
04/18/2022 |
Approve Plans & Specifications and Order Advertisement |
|
for Bids |
05/10/2022 |
Open Bids |
05/16/2022 |
Accept Bid |
06/22-10/22 |
Construction of Improvements |
10/2022 |
Assess Improvements |
05/2023 |
First Assessment Payment Due with Real Estate Taxes |
Recommended Council Action
By motion, approve the Resolution.
Strategic Plan Relationship
This project aligns with the City’s strategic plan goal of well-maintained infrastructure by providing high-quality street surfaces.
Board/Commission Review
Not required
Financial Impact
The project will be funded by a combination of assessments, bond proceeds placed in the City Pavement Management Program fund, and Public Utility Funds. There are sufficient funds to cover these costs.
Public Outreach/Input
The project is being conducted pursuant to MN Statutes, Chapter 429 and is compliant with all public notification requirements thereof.
Staff Recommendation
By motion, adopt the resolution.
Attachment List
Attached to this item is a project location map and feasibility report.
Body
WHEREAS, pursuant to Resolution No. 20-135 adopted on the 20th day of September, 2021, by the Blaine City Council, a report has been prepared for the City of Blaine Engineering Department, with reference to the reconstructions of 97th Avenue from Hamline Avenue to Yalta Street, 97th Lane from Hamline Avenue to Xebec Street, 97th Court from West cul-de-sac to Hamline Avenue, 98th Avenue from Hamline Avenue to Xebec Street, 98th Lane from Wake Street to Yalta Street, 99th Avenue from Wake Street to Xebec Street, 99th Lane from Xebec Street to Austin Street, Hamline Avenue from Edgewood Road to North cul-de-sac, Wake Street from 98th Avenue to 99th Avenue, Wake Court from 99th Avenue to North cul-de-sac, Xebec Street from Edgewood Road to 99th Lane, Yalta Street from 97th Avenue to 99th Lane and this report received by the Council on the 20th Day of December, 2021.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
1. The Council will consider the improvement in accordance with the report finding the improvement necessary, cost-effective, and feasible, resulting in a benefit to the properties proposed to be assessed and will consider the assessment of benefiting property for all or a portion of the cost of the improvement pursuant to the Minnesota Statutes, Chapter 429, at an estimated total cost of the improvement of $4,889,565.00.
2. A Public Hearing shall be held on such proposed improvement on the19th day of January, 2022, at 7:30 PM in the Council Chambers of City Hall, and the City Clerk shall give mailed and published notice of such hearing and improvement as required by law.
PASSED by the City Council of the City of Blaine this 20th day of December, 2021.