File #: RES 21-019    Version: 1 Name: Rcv Feas Rpt - Order Pub Hrg for 2021 Street Reconstructions, I/P 21-06
Type: Resolution Status: Passed
File created: 2/1/2021 In control: City Council
On agenda: 2/1/2021 Final action: 2/1/2021
Title: RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE 2021 STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT NO. 21-06
Sponsors: Dan Schluender
Attachments: 1. Project Location Map, 2. 2021 Street Reconstructions Feasibility Report

ADMINISTRATION - Dan Schluender, City Engineer

 

Title

RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE 2021 STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT NO. 21-06

 

Background

At the council meeting held on September 21, 2020, council initiated this project and ordered the preparation of a Feasibility Report. 

 

The report outlines the 2021 Street Reconstructions project consisting of reconstructing the following streets:

 

                     Club West Parkway from 109th Avenue to Cloud Drive

                     105th Lane from National Street to Sunset Avenue

                     Flanders Court from Radisson Road to 100th Court

                     100th Court from Flanders Court to cul-de-sac

                     93rd Lane Extension from approximately 250 feet east of Anoka County - Blaine Airport Gate A to 85th Avenue

 

The project area consist of a mix of city streets with concrete curb and gutter, a city street with no curb and gutter and a rural section street with no curb and gutter and two State Aid collector routes.  The proposed improvements generally include:

 

                     Club West Parkway - spot curb replacement, bituminous pavement replacement, renovation to the existing roundabout, minor storm sewer improvments

                     105th Lane - installing concrete curb and gutter, bituminous pavement replacement, additional catch basins and storm sewer pipe

                     Flanders Court - spot curb replacement and bituminous pavement replacement

                     100th Court - spot curb replacement and bituminous pavement replacement

                     93rd Lane Extension - spot curb replacement on medians and bituminous pavement replacement

 

The estimated cost of these proposed improvements is $5,519,260 with $1,017,348 proposed to be assessed to the benefitting properties over a 15-year period.  Replacement of sanitary sewer castings and minor water main work at an estimated cost of $172,654 is proposed to be paid from the City’s Public Utility Funds.  The remaining portion of $4,329,258 is proposed to be paid from the City’s Pavement Management Program Fund and City Municipal State Aid Funds.

 

The project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.

 

Schedule of Actions

09/21/2020

Initiate Project and Order Preparation of Feasibility Report

02/01/2021

Receive Feasibility Report and Order Public Hearing

02/15/2021

Hold Public Hearing, Order Improvement, and

 

Order Preparation of Plans and Specifications

04/19/2021

Approve Plans & Specifications and Order Advertisement

 

for Bids

05/18/2021

Open Bids

06/07/2021

Accept Bid

06/21-10/21

Construction of Improvements

10/2021

Assess Improvements

01/2022

First Assessment Payment Due with Real Estate Taxes

 

Recommendation

By motion, adopt the resolution.

 

Body

WHEREAS, pursuant to Resolution No. 20-134 adopted on the 21st day of September, 2020, by the Blaine City Council, a report has been prepared for the City of Blaine Engineering Department, with reference to the 2021 Street Reconstructions consisting of Club West Parkway NE from 109th Avenue NE to Cloud Drive NE, 93rd Lane Extension from approximately 250 feet east of Anoka County - Blaine Airport Gate A to 85th Avenue NE, 100th Court NE from Flanders Court NE to cul-de-sac, Flanders Court NE from Radisson Road NE to 100th Court NE and 105th Lane NE from National Street NE to Sunset Avenue and this report received by the Council on the 1st day of February, 2021.

                     

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The Council will consider the improvement in accordance with the report finding the improvement necessary, cost-effective, and feasible, resulting in a benefit to the properties proposed to be assessed and will consider the assessment of benefiting property for all or a portion of the cost of the improvement pursuant to the Minnesota Statutes, Chapter 429, at an estimated total cost of the improvement of $5,519,260.

 

2.                     A Public Hearing shall be held on such proposed improvement on the 15th day of February, 2021, at 7:30 PM in the Council Chambers of City Hall, and the City Clerk shall give mailed and published notice of such hearing and improvement as required by law.

 

PASSED by the City Council of the City of Blaine this 1st day of February, 2021.