File #: RES 19-169    Version: 1 Name: Initiate Project & Order Feasibility for 2020 Street Reconstructions-Area 2, I/P 19-18
Type: Resolution Status: Passed
File created: 10/7/2019 In control: City Council
On agenda: 10/7/2019 Final action: 10/7/2019
Title: INITIATE PROJECT AND ORDER PREPARATION OF FEASIBILITY REPORT FOR THE 2020 STREET RECONSTRUCTIONS - AREA 2, IMPROVEMENT PROJECT NO. 19-18
Sponsors: Dan Schluender
Attachments: 1. Location Map.pdf

ADMINISTRATION - Dan Schluender, City Engineer

 

Title

INITIATE PROJECT AND ORDER PREPARATION OF FEASIBILITY REPORT FOR THE 2020 STREET RECONSTRUCTIONS - AREA 2, IMPROVEMENT PROJECT NO. 19-18

 

Background

At the September 16, 2019 City Council workshop, staff brought forward a list of proposed projects for the 2020 Pavement Management Program (PMP).  The 2020 Street Reconstructions - Area 2 project consists of reconstruction of the following streets:

 

                     Taylor Street from 129th Avenue to 132nd Lane

                     Pierce Street from Taylor Street to 132nd Lane

                     Lincoln Street from 131st Lane to 132nd Lane

                     Johnson Street from 131st Lane to 132nd Lane

                     129th Lane from Polk Street to Taylor Street

                     131st Lane from Lincoln Street to Central Avenue

                     132nd Avenue from Jonson Street to Central Avenue

                     132nd Lane from Taylor Street to Central Avenue

 

The streets are all residential streets with concrete curb and gutter which have reached the end of their service lives.  The proposed project would fully reconstruct all of the streets in 2020.

 

If approved, this Resolution initiates the proposed 2020 Street Reconstructions - Area 2 and orders the preparation of a feasibility report.

 

Recommended Council Action

By motion, approve the Resolution.

 

Body

WHEREAS, the City Council is aware of the need to maintain City streets in a condition that provides for functional, safe and efficient travel; and

 

WHEREAS, the City Council has determined that it is in the public interest to implement a Pavement Management Program to maintain City streets in a logical and cost-efficient manner; and

 

WHEREAS, the City Council adopted a Pavement Management Policy by Resolution No. 10-87 on October 7, 2010 to serve as the framework for implementing a Pavement Management Program; and

 

                     WHEREAS, the Blaine City Council proposes to initiate a street improvement project for the 2020 Street Reconstructions - Area 2; and

 

                     WHEREAS, it is proposed to assess the benefited property for all or a portion of the costs of the improvements, pursuant to Minnesota Statutes Chapter 429; and

 

                     NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Blaine that the proposed improvements are hereby referred to the City Engineer to provide the Council with a Feasibility Report and to advise the Council in a preliminary way as to whether the proposed improvements are necessary, cost-effective, and feasible, and the estimated cost of the improvements as recommended.

 

PASSED by the City Council of the City of Blaine this 7th day of October, 2019.