Blaine logo
File #: RES 19-123    Version: 1 Name: Accept Bid for Wellhouse 1, 2 & 9 Rehab I/P 19-15
Type: Resolution Status: Passed
File created: 8/5/2019 In control: City Council
On agenda: 8/5/2019 Final action: 8/5/2019
Title: ACCEPT BID FROM MUNICIPAL BUILDERS, INC. IN THE AMOUNT OF $2,642,000.00 FOR WELLHOUSE 1, 2 AND 9 REHABILITATION, IMPROVEMENT PROJECT NO. 19-15
Sponsors: Dan Schluender
Attachments: 1. Blaine Wellhouse Location Map

ADMINISTRATION - Jon Haukaas, Director of Public Works

 

Title

ACCEPT BID FROM MUNICIPAL BUILDERS, INC. IN THE AMOUNT OF $2,642,000.00 FOR WELLHOUSE 1, 2 AND 9 REHABILITATION, IMPROVEMENT PROJECT NO. 19-15

 

Background

Bids were received at 2:00 PM, July 30, 2019, for Wellhouse 1, 2 and 9 Rehabilitation, Improvement Project No. 19-15.  A total of 2 bids were received ranging from $2,642,000.00 to $2,693,200.00.  The Engineer’s estimate for construction and three lowest bidders are as follows:

 

Engineer’s Estimate

$2,610,000.00

Municipal Builders, Inc.

$2,642,000.00

Rice Lake Construction

$2,693,200.00

 

Bids have been checked and tabulated, and it has been determined that Municipal Builders, Inc. of Andover, Minnesota is the lowest bidder.  The Engineering Department has worked with Municipal Builders, Inc. on previous contracts.  Staff recommends the low bid be accepted and a contract entered into with Municipal Builders, Inc. 

 

City Council is also asked to approve a 10% contingency to bring the total project budget to $2,906,200.00.  The funding source for this project is Water Utilities funds and there are sufficient funds to cover these costs.

 

Recommendation

By motion, adopt the resolution.

 

Body

WHEREAS, pursuant to advertisement for bids for Improvement Project No. 19-15, said bids were received on July 30, 2019, opened and tabulated according to law, and the following two lowest bids were received complying with the advertisement:

 

Municipal Builders, Inc.

$2,642,000.00

Rice Lake Construction

$2,693,200.00

 

AND WHEREAS, Municipal Builders, Inc. of Andover, Minnesota is the lowest responsible bidder.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The Mayor and City Manager are hereby authorized and directed to enter into a contract with Municipal Builders, Inc. for the designated improvements in the amount of $2,642,000.00.

 

2.                     A 10% contingency is hereby approved to bring the total project budget to $2,906,200.00 and the Director of Public Works is hereby authorized to sign all change orders up to the authorized project budget amount.

 

3.                     The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bonds submitted with their bids, except the two lowest bidders.  When a contract is duly executed, the bid bonds of the remaining unsuccessful bidder will be returned.  The bid bond of the successful bidder will be retained until the performance and payment bonds have been executed and approved, after which the bid bond will be returned.

 

PASSED by the City Council of the City of Blaine this 5th day of August, 2019.