File #: RES 17-109    Version: 1 Name: Declare Cost To Be Assessed & Call for Hearing-Project 14-14
Type: Resolution Status: Passed
File created: 8/3/2017 In control: City Council
On agenda: 8/3/2017 Final action: 8/3/2017
Title: DECLARE COST TO BE ASSESSED, ORDER PREPARATION AND CALL FOR HEARING ON PROPOSED ASSESSMENT FOR TRUNK UTILITY IMPROVEMENTS TO SERVE THE NORTH HALF OF THE NORTHEAST QUARTER OF SECTION 23 AND THE PLAT OF GLENN MEADOWS, IMPROVEMENT PROJECT NO. 14-14
Sponsors: Jean Keely
Attachments: 1. 14-14 Final Roll.pdf, 2. Assessed Parcels.pdf
Related files: RES 15-010, RES 15-036, RES 15-051, MO 15-056, RES 15-161, RES 17-117

ADMINISTRATION - Jean M. Keely, City Engineer

 

Title

 

DECLARE COST TO BE ASSESSED, ORDER PREPARATION AND CALL FOR HEARING ON PROPOSED ASSESSMENT FOR TRUNK UTILITY IMPROVEMENTS TO SERVE THE NORTH HALF OF THE NORTHEAST QUARTER OF SECTION 23 AND THE PLAT OF GLENN MEADOWS, IMPROVEMENT PROJECT NO. 14-14

 

Background

Project No. 14-14 includes trunk and lateral sanitary sewer and trunk and lateral water main, and appurtenant construction.  The total cost of the project is as follows:

 

Construction Costs………………….

$1,016,457.18

Engineering Costs…………………

$   173,598.01

Interest……………………………...

$     40,592.00

Administration, Assessing, Other…...

$     95,016.67

Total…………………………………

$1,325,663.86

 

The total project cost indicated in the Feasibility Report was $1,011,546.00.

 

Project costs were higher than estimated due to winter construction caused by delays in the wetland permitting process, wetter than normal climate, and a tight completion date.  The assessment roll has been prepared consistent with the Feasibility Report.  Of the total cost, the amount to be assessed is $762,062.46. The Public Utility Fund will contribute $50,000.00 for water main oversizing.  Pooled TIF/EDA Funds will contribute $116,288.50 for platted Austin Street and $397,312.90 for water main.

 

Any parcels that connect directly to the water main or the sanitary sewer in the future will pay the typical lateral connection charge.

 

Recommendation

By motion, adopt the resolution.

 

Body

WHEREAS, a contract has been entered into for construction of trunk and lateral sanitary sewer, and trunk and lateral water main, and appurtenant construction in the following described area:

 

On the Austin Street NE Alignment from Pheasant Ridge Drive to the 112th Avenue alignment in the plat of Glenn Meadows to serve the North Half of the Northeast Quarter of Section 23 abutting Lexington Avenue and 109th Avenue, and the Plats of Glenn Meadows Addition, Corrected Plat of Sanctuary Preserve, Sanctuary Preserve 2nd and Sanctuary Preserve 3rd (South Half of Section 14) abutting Lexington Avenue and 109th Avenue

 

AND WHEREAS, the construction cost for such improvement is $1,016,457.18 and the expenses incurred in the making of said improvements amount to be $309,206.68 making the total cost $1,325,663.86.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The total cost of such improvement is hereby declared to be $1,325,663.86.

 

2.                     The amount to be assessed is hereby declared to be $762,062.46.  The Public Utility Fund will contribute $50,000.00.  TIF & EDA Funds contribution is $513,601.40.

 

3.                     Assessments shall be payable in annual installments extending over a period of ten (10) years, the first of the installments to be payable on or before the first Monday in January 2018, and shall bear interest at the rate of four and five tenths percent (4.5%) per annum from the date of the adoption of the assessment resolution.

 

4.                     Assessments on PINS 14-31-23-43-0002, 14-31-23-44-0002, 23-31-23-11-0001, and 23-31-23-12-0001 will be deferred until developed.  Upon development the assessment will become current along with interest charged at the rate of four and five tenths percent (4.5) from the date of adoption of this resolution through the year in which the deferral is terminated.  The interest will be added to the principal of the assessment and spread over a period of ten (10) years.  To each subsequent installment when due shall be added interest for one (1) year on all unpaid installments.

 

5.                     The City Manager shall forthwith calculate the proper amount to be specially assessed for such improvement against every assessable lot, piece, or parcel of land within the district affected without regard to cash valuation, as provided by law, and he shall file a copy of such proposed assessment in his office for public inspection.

 

6.                     The City Manager has notified the City Council that such proposed assessment has been completed and filed in his office for public inspection.

 

7.                     A hearing shall be held on the 7th day of September, 2017, in the Council Chambers at the Blaine City Hall at 7:30 PM, or as near that time as possible, to pass upon the proposed assessment at such time and place all persons owning property affected by such improvement will be given an opportunity to be heard with reference to such assessment.

 

8.                     The City Manager shall give published and mailed notice of such hearing as required by law.

 

PASSED by the City Council of the City of Blaine this 3rd day of August 2017.