File #: RES 13-152    Version: 1 Name: Oak Park Blvd. Call for Hearing Oak Park Blvd.-Call for Hearing
Type: Resolution Status: Passed
File created: 9/5/2013 In control: City Council
On agenda: 9/5/2013 Final action: 9/5/2013
Title: CALL FOR HEARING ON PROPOSED ASSESSMENT FOR RECONSTRUCTION OF OAK PARK BOULEVARD/119TH AVENUE FROM 125TH AVENUE TO JEFFERSON STREET IMPROVEMENT PROJECT NO. 11-12
Sponsors: Jean Keely, Dan Schluender
Attachments: 1. 11-12 Order&Call Roll.pdf, 2. 11-12 Assessment Map.pdf
Related files: RES 13-168, RES 13-150
ITEM:         12.5  B         ADMINISTRATION - Jean M. Keely, City Engineer
 
Title
CALL FOR HEARING ON PROPOSED ASSESSMENT FOR
RECONSTRUCTION OF OAK PARK BOULEVARD/119TH AVENUE FROM 125TH AVENUE TO JEFFERSON STREET
IMPROVEMENT PROJECT NO. 11-12
 
Background
Project No. 11-12 includes spot concrete curb and gutter replacement, spot concrete sidewalk replacement, storm sewer structures, asphalt surface, traffic control signage, striping, and appurtenant construction for Oak Park Boulevard and 119th Avenue from 125th Avenue to Jefferson Street.
The estimated total cost of the project is as follows:
 
Construction Costs………………….
$1,093,537.68
Engineering Costs…………………
$   119,801.46
Interest……………………………...
$       6,693.92
Administration, Assessing, Other…...
$     59,164.63
Total…………………………………
$1,279,197.69
 
The total project cost indicated in the Feasibility Report was $1,393,200.00.
 
The Assessment Roll has been prepared consistent with the Feasibility Report, except that the three park parcels were taken off of the assessment roll.  The City's Assessment Policy states that the City will not levy assessments against City owned property that is maintained and operated out of the City's General Fund Budget.  The park parcels meet this criteria and their removal from the assessment roll does not change the assessments to other parcels, but increases the Municipal State Aid (MSA) contribution.    Of the estimated total cost, the amount to be assessed is $128,566.40. The Public Utility Fund will contribute $86,898.60 for water and sewer improvements.  MSA contribution is $1,063,732.69.
 
Recommendation
By motion, approve the resolution.
 
Body
 
WHEREAS, pursuant to Resolution No. 13-151 passed by the Blaine City Council on September 5, 2013, the City Manager was directed to prepare a proposed assessment of the cost for partial reconstruction of the existing street section to include spot concrete curb and gutter replacement, replacement/reconstruction of various storm and sanitary sewer structures, replacement of hydrants, spot concrete sidewalk replacement, asphalt pavement replacement, traffic control signage and striping, and related appurtenant construction in the following described area:
 
Oak Park Boulevard/119th Avenue from 125th Avenue to Jefferson Street
 
AND WHEREAS, the City Manager has notified the City Council that such proposed assessment has been completed and filed in his office for public inspection.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      A hearing shall be held on the 3rd day of October, 2013, in the Council Chambers at Blaine City Hall at 8:00 PM, or as near that time as possible, to pass upon such proposed assessment at such time and place all persons owning property affected by such improvement will be given an opportunity to be heard with reference to such assessment.
 
2.      The City Manager shall give published and mailed notice of such hearing as required by law.
 
PASSED by the City Council of the City of Blaine this 5th day of September, 2013.