File #: RES 13-115    Version: 1 Name: Award Davenport Bid
Type: Resolution Status: Passed
File created: 6/20/2013 In control: City Council
On agenda: 6/20/2013 Final action: 6/20/2013
Title: ACCEPT BID FROM NORTH VALLEY, INC. IN THE AMOUNT OF $888,515.72 FOR THE RECONSTRUCTION OF DAVENPORT STREET FROM 99TH LANE TO 105TH AVENUE IMPROVEMENT PROJECT NO. 11-11
Sponsors: Jean Keely
Attachments: 1. Davenport Location Map
Related files: RES 12-054, RES 13-011
ITEM:         12.4         ADMINISTRATION - Jean M. Keely, City Engineer
 
Title
ACCEPT BID FROM NORTH VALLEY, INC. IN THE AMOUNT OF $888,515.72 FOR THE RECONSTRUCTION OF DAVENPORT STREET FROM 99TH LANE TO 105TH AVENUE
IMPROVEMENT PROJECT NO. 11-11
 
Background
Bids were received at 11:30 AM, June 4, 2013, for Project No. 11-11.  A total of six bids were received ranging from $888,515.72 to $1,052,109.81.  The Engineer's estimate for construction and three lowest bidders are as follows:
 
Engineer's Estimate - Construction Cost
$1,112,000.00
North Valley, Inc.
$   888,515.72
C.S. McCrossan Construction, Inc.
$   941,939.36
Rum River Contracting
$   983,205.59
 
Bids have been checked and tabulated, and it has been determined that North Valley, Inc. of Nowthen, Minnesota is the lowest bidder. The Engineering Department has worked with North Valley, Inc. on previous contracts.  I recommend the low bid be accepted and a contract entered into with North Valley, Inc.
 
City Council is also asked to approve a 10% contingency to bring the total project budget to $977,367.
 
It is proposed to assess approximately $499,000 of the total project cost. Additional funding sources for this project are the City's Public Utility funds, Pavement Management Program funds, and Municipal State Aid Street funds, and there are sufficient funds to cover these costs.
 
Recommendation
By motion, approve the resolution.
 
Body
WHEREAS, pursuant to advertisement for bids for Improvement Project No. 11-11, said bids were received on June 4, 2013, opened and tabulated according to law, and the following three lowest bids were received complying with the advertisement:
 
North Valley, Inc.
$   888,515.72
C.S. McCrossan Construction, Inc.
$   941,939.36
Rum River Contracting
$   983,205.59
 
AND WHEREAS, North Valley, Inc. of Nowthen, Minnesota is the lowest responsible bidder.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      The Mayor and City Manager are hereby authorized and directed to enter into a contract with North Valley, Inc. for the designated improvements in the amount of $888,515.72.
 
2.      A 10% contingency is hereby approved to bring the total project budget to $977,367 and the Public Services Manager is hereby authorized to sign all change orders up to the authorized project budget amount.
 
3.      The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bonds submitted with their bids, except the three lowest bidders.  When a contract is duly executed, the bid bonds of the two remaining unsuccessful bidders will be returned.  The bid bond of the successful bidder will be retained until the performance and payment bonds have been executed and approved, after which the bid bond will be returned.
 
PASSED by the City Council of the City of Blaine this 20th day of June, 2013.