File #: RES 13-022    Version: 1 Name: Receive 2013 Bit Overlay Feasibility Rpt
Type: Resolution Status: Passed
File created: 2/21/2013 In control: City Council
On agenda: 2/21/2013 Final action: 2/21/2013
Title: RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE 2013 PAVEMENT MANAGEMENT PROGRAM - BITUMINOUS OVERLAY, IMPROVEMENT PROJECT NO. 13-01
Sponsors: Jean Keely
Attachments: 1. 2013 Bituminous Overlay Map.pdf, 2. 2013 Overlay Feasibility Report.pdf
Related files: RES 13-007, RES 13-084, RES 13-035, RES 13-039
ITEM:         12.2         ADMINISTRATION - Jean M. Keely, City Engineer
 
Title
RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE 2013 PAVEMENT MANAGEMENT PROGRAM - BITUMINOUS OVERLAY, IMPROVEMENT PROJECT NO. 13-01
 
Background
The proposed improvements include a 1½ inch bituminous overlay, edge milling, spot curb replacement and appurtenant construction on various city streets.  The estimated total cost of the project is $1,157,255 with $403,002.50 proposed to be assessed over a five year period.  The proposed assessment rate is a flat rate of $535.05 per residential lot unit or $10.70 per front foot for parcels zoned commercial/industrial and multi-family residential.  The remaining portion of $754,252.50 is proposed to be paid from the City's Pavement Management Program Funds.  The project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.
 
Schedule of Actions
01/03/13
Initiate Project and Order Preparation of Feasibility Report
02/21/13
Receive Feasibility Report and Order Public Hearing
03/06/13
Hold Public Information Meeting
03/21/13
Hold Public Hearing, Order Improvement, and
 
Order Preparation of Plans and Specifications
03/21/13
Approve Plans and Specifications and Order
 
Advertisement for Bids
04/23/13
Open Bids
05/16/13
Accept Bid
06-09/2013
Construct Improvements
10/2013
Assess Improvements
2014
First Assessment Payment Due with Real Estate Taxes
 
Recommendation
By motion, adopt the resolution.
 
Body
WHEREAS, pursuant to Resolution No. 13-007 adopted on the 3rd day of January, 2013, by the Blaine City Council, a report has been prepared by the City of Blaine, Engineering Department, with reference to the 2013 Pavement Management Program -Bituminous Overlay of various city streets, and this report received by the Council on the 21st day of February, 2013.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      The Council will consider the improvement in accordance with the report finding the improvement necessary, cost-effective, and feasible and resulting in a benefit to the properties proposed to be assessed, and will consider the assessment of benefiting property for all or a portion of the cost of the improvement pursuant to the Minnesota Statutes, Chapter 429, at an estimated total cost of the improvement of $1,157,255.
 
2.      A Public Hearing shall be held on such proposed improvement on the 21st day of March, 2013, at 8:00 PM in the Council Chambers of City Hall, and the City Clerk shall give mailed and published notice of such hearing and improvement as required by law.
 
PASSED by the City Council of the City of Blaine this 21st day of February, 2013.