File #: RES 15-100    Version: 1 Name: Order Improvement for Project 15-11 Order Improvement for 15-11
Type: Resolution Status: Passed
File created: 6/4/2015 In control: City Council
On agenda: 6/4/2015 Final action: 6/4/2015
Title: ORDER IMPROVEMENT FOR PARTIAL RECONSTRUCTION OF 87TH AVENUE IN THE CITY OF CIRCLE PINES, IMPROVEMENT PROJECT NO. 15-11
Sponsors: Jean Keely
Attachments: 1. Circle Pines 2015 Street Improvement Project - Figure 1.pdf
Related files: RES 15-061, RES 15-077, RES 16-130, RES 16-137
PUBLIC HEARING - Jean M. Keely, City Engineer
 
Title
ORDER IMPROVEMENT FOR PARTIAL RECONSTRUCTION OF 87TH AVENUE IN THE CITY OF CIRCLE PINES, IMPROVEMENT PROJECT NO. 15-11
 
Schedule of Actions
 
04/02/15
Initiate Project and Order Preparation of Feasibility Report
05/07/15
Receive Feasibility Report and Order Public Hearing
06/04/15
Hold Public Hearing, Order Improvement, and Approve Joint
 
Powers Agreement with Circle Pines
06/09/15
Circle Pines to Construct Improvements
09/2015
Assess Improvements
2016
First Assessment Payment Due with Real Estate Taxes
 
Background
Notice for this hearing has been published and mailed.  In 2015, the City of Circle Pines will be reconstructing 87th Avenue as part of their 2015 Street Improvement Project.  The entire right of way for this section of 87th Avenue (just east of the portion of 87th Avenue reconstructed by Circle Pines six years ago) is within the City of Circle Pines but provides access to three Blaine single family parcels which were platted as Golden Lake Estates Second Addition in 1987.  The City of Circle Pines has asked the City of Blaine to assess a portion of their project cost to the three parcels in Blaine that they feel benefit from their project.
 
The proposed improvements include partial reconstruction with spot curb and gutter replacement, removal of the existing pavement, subgrade correction as needed and installation of 3.5 inches of new bituminous pavement.  The estimated cost of the Circle Pines project is $1,379,600.00.
 
It is proposed to assess the three benefitting properties in the City of Blaine over a ten-year period in accordance with the City of Blaine's Assessment Policy.  The City of Blaine has a similar partial reconstruction project (15-07) on 92nd Circle in the plat of Hidden Lake Estates.  It is proposed to assess the same per lot rate to the three Blaine parcels on 87th Avenue as proposed to be assessed for Improvement Project No. 15-07.  An estimate of $1,042.61 per parcel will be assessed against the three properties within the City of Blaine for a total of $3,127.83.
 
The project is necessary, cost-effective, feasible, and will result in a benefit for the properties proposed to be assessed.
 
Recommendation
Conduct public hearing and, by motion, adopt the resolution.
 
Body
WHEREAS, Resolution No. 15-077 of the Blaine City Council, adopted on the 7th day of May, 2015 ordered a public hearing on the proposed project; and
 
WHEREAS, the required notices were published and mailed to benefiting property owners, and the public hearing was held on the 4th day of June 2015, at which time all persons desiring to be heard were given an opportunity to be heard.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      Such improvements are hereby ordered as proposed in the Feasibility Report, which was accepted by Resolution No. 15-077 adopted on the 7th day of May, 2015.
 
PASSED by the City Council of the City of Blaine this 4th day June, 2015.