File #: MO 18-137    Version: 2 Name: Senior Center start date
Type: Motion Status: Passed
File created: 11/15/2018 In control: City Council
On agenda: 11/15/2018 Final action: 11/15/2018
Title: SELECT CONSTRUCTION START DATE FOR SENIOR CENTER PROJECT
Sponsors: Bob Therres
Attachments: 1. Site Layout

ADMINISTRATION- Robert Therres, Public Services Mgr./Asst. City Manager

 

Title

SELECT CONSTRUCTION START DATE FOR SENIOR CENTER PROJECT

 

Background

With the construction of the new Senior Center scheduled for 2019, the Blaine Festival has requested that construction not start until after the 4th of July holiday as it is there 50th anniversary year.  According to our architect, 292 Design, and general contractors they work with, this would have a financial impact on the project and might result in fewer bidders.

 

At the workshop discussion on November 1st, the City Council requested that staff work with the Blaine Festival to mitigate construction impacts on the Festival, scheduled for June 28th-30th, 2019.

 

Staff has had the opportunity to meet with the Festival on this issue.  The Festival requests that the construction site by cleaned up and secured by June 22nd so they have time to bring in and set up their Festival.  They also requested to just fence off/secure the building site and leave the new senior parking area accessible for storage/set up.  Attached is a drawing of the senior center site that will be fenced.

 

Staff will continue to work with all parties in Aquatore Park to address any issues caused by the new construction.

 

Recommendation

By motion, direct that construction start for the Senior Center project in the spring of 2019.