Blaine logo
File #: MO 22-208    Version: 1 Name: Accept Design & Construction Svcs Proposal for 2023 Southeast Area Street Reconstructions, I/P 23-08
Type: Motion Status: Passed
File created: 12/19/2022 In control: City Council
On agenda: 12/19/2022 Final action: 12/19/2022
Title: Authorize the Mayor and City Manager to Enter into a Contract with WSB & Associates, Inc. for Professional Design and Construction Services for the 2023 Southeast Area Street Reconstructions Improvement Project, Improvement Project No. 23-08
Sponsors: Dan Schluender
Attachments: 1. Location Map, 2. 23-08 WSB Final Design and Construction Proposal

Administration - Dan Schluender, City Engineer

 

Title

Title

Authorize the Mayor and City Manager to Enter into a Contract with WSB & Associates, Inc. for Professional Design and Construction Services for the 2023 Southeast Area Street Reconstructions Improvement Project, Improvement Project No. 23-08

end

 

Executive Summary

Council is requested to approve a contract with WSB & Associates, Inc. (WSB) for professional services for final design and construction services for the 2023 Southeast Area Street Reconstructions, Improvement Project No. 23-08, in the amount of $367,628.00. 

 

Background

On August 1, 2022 Council initiated the 2023 Southeast Area Street Reconstructions project, Project No. 23-08 with Resolution No. 22-131. At the August 15, 2022 Council meeting WSB, which is one of the engineering firms in the pre-approved consultant pool approved by Council on August 2, 2021, was awarded a contract to prepare preliminary design and a feasibility report. At that time it was stated that after completion of the feasibility report and upon ordering the improvements, a contract for final design and construction services would be negotiated with WSB.

 

The Engineering Department recently requested and received a proposal for final design and construction services including construction materials testing for the 2023 Southeast Area Street Reconstructions project from WSB in the amount of $367,628.00. WSB is in the council approved engineer consultant pool.  Staff has reviewed this proposal and determined that the fees are justified and reasonable. City council is also asked to approve a 10% contingency to bring the total project budget to $404,391.00

 

This project will be funded through proposed project assessments, Pavement Management Program funds, and Public Utility funds.

 

Strategic Plan Relationship

This project aligns with the City’s strategic plan goal of well-maintained infrastructure by providing high quality city streets.

 

Board/Commission Review

Not required.

 

Financial Impact

The funding source for these improvements will be project assessments, Pavement Management Program funds, and Public Utility funds. There are sufficient funds to cover these costs.

 

Public Outreach/Input

The project is being conducted pursuant to MN Statutes, Chapter 429 and is compliant with all public notification requirements thereof.

 

Staff Recommendation

By motion, authorize the Mayor and City Manager to enter into a contract with WSB & Associates, Inc. in the amount of $367,628.00 for final design and construction services for the 2023 Southeast Area Street Reconstructions project, Improvement Project No. 23-08.  In addition, authorize a 10% contingency to bring the total project budget to $404,391.00 and authorize the City Manager or their designee to sign all change orders up to the authorized project budget amount.

 

 