Title: ORDER IMPROVEMENT AND ORDER PREPARATION OF PLANS AND SPECIFICATIONS FOR THE 93RD LANE INDUSTRIAL PARK AREA STREET IMPROVEMENTS, PHASE 3, IMPROVEMENT PROJECT NO. 13-24
Sponsors: Jean Keely
Attachments: 1. location map.pdf
Related files: RES 14-093, RES 14-064, RES 13-182, RES 15-150, RES 15-164
ITEM:         9.2         PUBLIC HEARING - Jean M. Keely, City Engineer
 
Title
ORDER IMPROVEMENT AND ORDER PREPARATION OF PLANS AND SPECIFICATIONS FOR THE 93RD LANE INDUSTRIAL PARK AREA STREET IMPROVEMENTS, PHASE 3, IMPROVEMENT PROJECT NO. 13-24
 
Background
Notice for this hearing has been published and mailed.  An informal open house meeting was held on April 29, 2014 and two property owners attended.  
 
The proposed improvements for this project include asphalt pavement replacement, gravel shouldering, storm drainage improvements, culvert replacements and cleaning, ditch cleaning and regrading, traffic control signage, and appurtenant construction of Baltimore Street from 91st Avenue to Eldorado Street, Radisson Road from Eldorado Street to 93rd Lane Extension, Eldorado Street from 91st Avenue to Radisson Road and Hastings Street from Radisson Road to the cul de sac.  The estimated total cost of the project is $823,900.00 with $269,378.85 proposed to be assessed amongst benefitting properties over a ten-year period using the front footage method for commercial/industrial properties as identified in the Public Improvement Special Assessment Policy.  Replacement of existing sanitary sewer castings/rings at an estimated cost of $10,250.00 is proposed to be paid for by the City Public Utility Fund. The remaining portion of $544,271.15 is proposed to be paid from the City's Pavement Management Program Funds.  
 
The project is necessary, cost-effective, feasible, and will result in a benefit for the properties proposed to be assessed.
 
Schedule of Actions
11/07/13
Initiate Project and Order Preparation of Feasibility Report
04/17/14
Receive Feasibility Report and Order Public Hearing
04/29/14
Hold Public/Business Information Meeting
05/15/14
Hold Public Hearing, Order Improvement, and
 
Order Preparation of Plans & Specifications
05/15/14
Approve Plans & Specifications and Order Advertisement for Bids
06/09/14
Open Bids
06/19/14
Accept Bid
2014
Construct Improvements
11/2014
Assess Improvements
2015
First Assessment Due with Real Estate Taxes
 
Recommendation
Conduct public hearing and, by motion, approve the resolution.
 
Body
WHEREAS, Resolution No. 14-064 of the Blaine City Council, adopted on the 17th day of April, 2014 , ordered a public hearing on the proposed project; and
 
WHEREAS, the required notices were published and mailed to benefiting property owners, and the public hearing was held on the 15th day of May, 2014, at which time all persons desiring to be heard were given an opportunity to be heard.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      Such improvements are hereby ordered as proposed in the Feasibility Report, which was accepted by Resolution No. 14-064 adopted on the 17th day of April, 2014.
 
2.      The City Engineer is hereby designated as the Engineer for this improvement and is directed to prepare plans and specifications for the making of this improvement.
 
3. The contract shall be awarded no later than May 14, 2015.
 
PASSED by the City Council of the City of Blaine this 15th day of May, 2014.