Title: GRANTING A CONDITIONAL USE PERMIT AMENDMENT TO ALLOW FOR EXPANSION OF OUTSIDE STORAGE OF BUSES AS PART OF A TRANSPORTATION TERMINAL AT 8600 XYLITE STREET NE. LORENZ BUS SERVICE. (CASE FILE NO. 17-0042/NBL)
Sponsors: Bryan Schafer

DEVELOPMENT BUSINESS - Bryan K. Schafer, Planning and Community Development Director

 

Title

GRANTING A CONDITIONAL USE PERMIT AMENDMENT TO ALLOW FOR EXPANSION OF OUTSIDE STORAGE OF BUSES AS PART OF A TRANSPORTATION TERMINAL AT 8600 XYLITE STREET NE.  LORENZ BUS SERVICE.  (CASE FILE NO. 17-0042/NBL)

 

Schedule of Actions

Planning Commission (Public Hearing)

03/13/18

City Council (Conditional Use Permit)

04/05/18

Action Deadline

04/09/18

 

Planning Commission

The Planning Commission voted unanimously to approve the Conditional Use Permit.  There were no comments at the public hearing.

 

Background

Conditional Use Permit

Lorenz Bus has operated their bus service garage and parking facility from this site for over 30 years. The business has grown over the years and they have run out of parking areas for both buses as well as employee vehicles. The use was issued a CUP (Conditional Use Permit) in 1988 for an expansion that will now be amended to allow for continued operation as well as the significant expansion of parking areas for buses and cars.

 

The new site plan shows two large parking expansions. The bus parking lot will be expanded to the rear (west) of the buildings and will be sized to handle 95 full size buses (generally 45-feet). This will eliminate most if not all of the bus parking that occurs up around the building sites and along Xylite. The new employee parking lot will be placed along the south side of the site closer to 85th Avenue. This new lot will access Xylite Street and will be sized to handle 200 stalls. This is larger than what is needed on a day to day basis but is sized to better handle the peak employee parking that occurs every August during the MN State Fair as well as other large metro wide events such as the recent Super Bowl.

 

The site plan has been designed to:

                     address storm water run-off by providing new pond areas and appropriate site grading.

                     new parking and drive surfaces with concrete curb and gutter

                     site landscaping

                     new fuel dispensing area and canopy (for bus refueling)

                     shows potential future building areas (not part of this approval) 

 

There is a small wetland area located in the northwest corner of the new bus parking area. The plan proposes to fill a portion of that wetland and provide off-site mitigation through the purchase of credits. This is being reviewed by the Rice Creek Watershed District and their permit is necessary before any Site Plan Approval is issued by the City. 

 

The site work will remove a significant area and number of trees to the west of the building areas. The landscape plan that has been shown will meet the tree replacement requirements.

 

This site has never paid Park Dedication as part if it’s development. This expansion is almost exclusively about adding additional parking rather than a significant building expansion. Because of that park dedication has not been added as a requirement at this time. However at the time any of the “future buildings” are proposed it would be appropriate to calculate and collect Park Dedication as part of those permits.

 

The water loop that is being routed around and back of the buildings will be required to be an 8-inch loop to provide adequate coverage for multiple buildings.

 

Variance Request

The existing parking and driveway along Xylite (between the building and east property line) is placed very near the property line with little or no setback. The setback requirement along this front yard area is 25-feet. The site plan for the new construction shows a consistent 12-5 foot setback between the new south driveway and middle driveway. This area will be curbed and landscaped. Staff is also recommending that this frontage receive a 7-foot high PVC coated chain link fence. The fence would be placed at or just inside the property line and would help screen/buffer the reduced setback. The variance that has been requested would allow the 12-5 foot setback and is supported by staff given the need to provide adequate paved surface to allow buses reasonable access to the overhead doors on the building.

 

Recommendation

By motion, approve the Resolution.

 

Attachments

See Report for Variance.

 

Body

                     WHEREAS, an application has been filed by Lorenz Bus Service as Conditional Use Permit Case File No. 17-0042; and

 

                     WHEREAS, a public hearing has been held by the Blaine Planning Commission on March 13, 2018; and

 

                     WHEREAS, the Blaine Planning Commission recommends said Conditional Use Permit be approved; and

 

                     WHEREAS, the Blaine City Council has reviewed said case on April 5, 2018.

 

                     NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Blaine that a Conditional Use Permit Amendment is hereby approved per Section 31.14(k) of the Zoning Ordinance to allow for expansion of transportation terminal and associated bus parking at 8600 Xylite Street NE based on the following conditions:

 

1.                     A 7-foot high PVC coated chain link fence to be placed along the east property line between the south and middle driveway. The fence color to be approved as part of Site Plan Approval.

2.                     Formal Site Plan Approval is required prior to any site work.

3.                     A permit from the Rice Creek Watershed District is required prior to any site work.

4.                     The site to be recalculated for WAC (Water Access Charge) payment based on the expansion of utilized area.

5.                     Once the site work is completed all parking of buses and vehicles to remain on approved hard surface (paved) areas.

6.                     All necessary building and fire permits to be obtained for construction of new fuel facility.

7.                     Future building construction shown is conceptual and will require a CUP amendment and site review prior to their permitting and construction.

8.                     Site Plan Approval requires submittal of financial guarantees and execution of SIPA (Site Improvement Performance Agreement) to ensure that all site improvements are constructed as shown. 

9.                     All business signage by separate review and permit.

10.                     The water loop that is being routed around and back of the building will be required to be an 8-inch loop to provide adequate coverage for multiple buildings.

11.                     The main office/bus repair building to be provided with a code compliant fire suppression system at the earliest of any of the following events:  a) significant alteration (not maintenance) or any additions to the main building requiring a building permit  b) at the time building permits are issued for construction of other buildings on the site or  c) by June 1, 2023.

12.                     The remaining two storage buildings will not require fire suppression at this time as they are expected to be removed to make way for new larger bus storage garage (shown in concept).

13.                      This site has never paid Park Dedication as part of its development. This approval is almost exclusively about adding additional parking rather than a significant building expansion. Because of that park dedication has not been added as a condition. However at the time any of the “future buildings” are proposed it would be appropriate to calculate and collect Park Dedication as part of those permits.

 

PASSED by the City Council of the City of Blaine this 5th day of April, 2018.