File #: RES 14-039    Version: 1 Name: Rcv 2014 Street Reconstructs Feas Rpt-Order Pub Hrg
Type: Resolution Status: Passed
File created: 3/6/2014 In control: City Council
On agenda: 3/6/2014 Final action: 3/6/2014
Title: RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE PAVEMENT MANAGEMENT PROGRAM - 2014 STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT NO. 14-07
Sponsors: Jean Keely
Attachments: 1. Location Map.pdf, 2. Feasibility Report.pdf
Related files: WS 13-59, RES 13-184, RES 14-091, RES 14-059, RES 14-193, RES 14-048, RES 14-194, RES 14-217
ITEM:         12.4         ADMINISTRATION - Jean M. Keely, City Engineer
 
Title
RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE PAVEMENT MANAGEMENT PROGRAM - 2014 STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT NO. 14-07
 
Background
The proposed improvements will partially reconstruct various city streets in the D. Erickson 4th Addition and Jackson Place plat areas.  The proposed improvements will include spot curb replacement, asphalt surface removal and replacement, aggregate base and appurtenant construction.  
 
The estimated total cost of the project is $675,000 with $130,155 proposed to be assessed over a ten-year period, using the unit method for residential properties as identified in the Public Improvement Special Assessment Policy.  Replacement of existing sanitary sewer structure castings/rings, at an estimated cost of $24,675, is proposed to be paid for by the City Public Utility Fund. The remaining portion of $520,170 is proposed to be paid from the City's Pavement Management Program Funds.  
 
The project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.
 
Schedule of Actions
11/07/13
Initiate Project and Order Preparation of Feasibility Report
03/06/14
Receive Feasibility Report and Order Public Hearing
03/18/14
Hold Public Information Meeting
04/03/14
Hold Public Hearing, Order Improvement, and
 
Order Preparation of Plans and Specifications
04/03/14
Approve Plans and Specifications and Order
 
Advertisement for Bids
05/05/14
Open Bids
05/15/14
Accept Bid
06-09/2014
Construct Improvements
10/2014
Assess Improvements
2015
First Assessment Payment Due with Real Estate Taxes
 
Recommendation
By motion, adopt the resolution.
 
Body
WHEREAS, pursuant to Resolution No. 13-184 adopted on the 7th day of November, 2013, by the Blaine City Council, a report has been prepared by the City of Blaine, Engineering Department, with reference to the Pavement Management Program - 2014 Street Reconstructions of various city streets, and this report received by the Council on the 6th day of March, 2014.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      The Council will consider the improvement in accordance with the report finding the improvement necessary, cost-effective, and feasible and resulting in a benefit to the properties proposed to be assessed, and will consider the assessment of benefiting property for all or a portion of the cost of the improvement pursuant to the Minnesota Statutes, Chapter 429, at an estimated total cost of the improvement of $675,000.
 
2.      A Public Hearing shall be held on such proposed improvement on the 3rd day of April, 2014, at 8:00 PM in the Council Chambers of City Hall, and the City Clerk shall give mailed and published notice of such hearing and improvement as required by law.
 
PASSED by the City Council of the City of Blaine this 6th day of March, 2014.