File #: RES 15-126    Version: 1 Name: ACCEPT BID FOR REALIGNMENT OF WEST CENTRAL AVE SERVICE RD, PROJECT 13-26
Type: Resolution Status: Passed
File created: 7/9/2015 In control: City Council
On agenda: 7/9/2015 Final action: 7/9/2015
Title: ACCEPT BID FROM DOUGLAS-KERR UNDERGROUND, LLC IN THE AMOUNT OF $208,280.80 FOR THE REALIGNMENT OF THE WEST CENTRAL AVENUE SERVICE ROAD FROM 85TH AVENUE TO APPROXIMATELY 600 FEET NORTH, IMPROVEMENT PROJECT NO. 13-26
Sponsors: Jean Keely
Attachments: 1. Location Map.pdf
Related files: RES 13-186, MO 15-115

ADMINISTRATION - Jean M. Keely, City Engineer

 

Title

ACCEPT BID FROM DOUGLAS-KERR UNDERGROUND, LLC IN THE AMOUNT OF $208,280.80 FOR THE REALIGNMENT OF THE WEST CENTRAL AVENUE SERVICE ROAD FROM 85TH AVENUE TO APPROXIMATELY 600 FEET NORTH, IMPROVEMENT PROJECT NO. 13-26

 

Background

Bids were received at 10:00 a.m., June 29, 2015, for Project No. 13-26.  A total of five bids were received ranging from $208,280.80 to $345,496.88.  The Engineer’s estimate for construction and three lowest bidders are as follows:

 

Engineer’s Estimate - Construction Cost

$204,800.00

Douglas-Kerr Underground, LLC

$208,280.80

Valley Paving, Inc.

$246,941.85

Midwest Asphalt Corporation

$251,563.00

 

Bids have been checked and tabulated, and it has been determined that Douglas-Kerr Underground, LLC of Mora, MN is the lowest bidder. The Engineering Department has worked with Douglas-Kerr Underground, LLC on previous contracts.  I recommend the low bid be accepted and a contract entered into with Douglas-Kerr Underground, LLC.

 

City Council is also asked to approve a 10% contingency to bring the total project budget to $229,109.00.  The funding source for this project is pooled TIF funds and there are sufficient funds to cover these costs.

 

Recommendation

By motion, adopt the resolution.

 

Body

WHEREAS, pursuant to advertisement for bids for Improvement Project No. 13-26, said bids were received on June 29, 2015, opened and tabulated according to law, and the following three lowest bids were received complying with the advertisement:

 

Douglas-Kerr Underground, LLC

$208,280.80

Valley Paving, Inc.

$246,941.85

Midwest Asphalt Corporation

$251,563.00

 

 

AND WHEREAS, Douglas-Kerr Underground, LLC of Mora, MN is the lowest responsible bidder.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The Mayor and City Manager are hereby authorized and directed to enter into a contract with Douglas-Kerr Underground, LLC for the designated improvements in the amount of $208,280.80.

2.                     A 10% contingency is hereby approved to bring the total project budget to $229,109.00 and the Public Services Manager is hereby authorized to sign all change orders up to the authorized project budget amount.

3.                     The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bonds submitted with their bids, except the three lowest bidders.  When a contract is duly executed, the bid bonds of the two remaining unsuccessful bidders will be returned.  The bid bond of the successful bidder will be retained until the performance and payment bonds have been executed and approved, after which the bid bond will be returned.

 

PASSED by the City Council of the City of Blaine this 9th day July, 2015.