File #: MO 15-146    Version: 1 Name: APPROVE CHANGE ORDER NO. 1 IN THE AMOUNT OF $TBD FOR IMPROVEMENT PROJECT NO. 15-06
Type: Motion Status: Passed
File created: 12/17/2015 In control: City Council
On agenda: 12/17/2015 Final action: 12/17/2015
Title: APPROVE CHANGE ORDER NO. 1 IN THE AMOUNT OF $18,476.99 FOR THE CONSTRUCTION OF HARPERS PARK, IMPROVEMENT PROJECT NO. 15-06
Sponsors: Jean Keely

ADMINISTRATION- Robert Therres, Public Services Manager

 

Title

APPROVE CHANGE ORDER NO. 1 IN THE AMOUNT OF $18,476.99 FOR THE CONSTRUCTION OF HARPERS PARK, IMPROVEMENT PROJECT NO. 15-06

 

Background

On August 31, 2015, a contract was awarded to Dunaway Construction in the amount of $124,947.40 for the construction of Harpers Park.

 

During construction, areas of unsuitable soil were discovered in the trail alignment which required removal and replacement.  Additional retaining walls were also required as the final grades changed with the construction of a house on 130th Court.  Final quantity measurements exceed some bid quantities and the 10% contingency authorized with contract award; therefore Change Order No. 1 was prepared for Council approval.

 

Recommendation

By motion, approve Change Order No. 1 to the contract for Improvement Project No 15-06 in the amount of $18,476.99, amending the total contract amount to $143,424.39 and authorizing the Public Services Manager to sign said Change Order No. 1.