ITEM:         12.1         ADMINISTRATION Robert Therres, Public Service Manager
 
Title
REJECT BID FOR LIFT STATION NO. 3  
IMPROVEMENT PROJECT NO. 12-07
 
Background
Bids were received at 10:00 a.m., May 21, 2013, for Project No. 12-07.  One bid was received with a bid price of $369,700.  The Engineer's estimate and the bid received are as follows:
 
Engineer's Estimate - Construction Cost
$225,000.00
Lametti & Sons, Inc.
$369,700.00
 
After talking with other contractors, the reason that only one bid was received was the work schedule.  Many contractors have their summer work schedule lined up and that a fall bid schedule would be better.  Due to the bid being substantially higher than the engineer estimate, I recommend that the bid be rejected, the bid bond returned to the bidder, and the project be re-bid at a later date.
 
Recommendation
By motion, approve the resolution.
 
Body
WHEREAS, pursuant to advertisement for bids for Improvement Project No. 12-07, said bid was received on May 21, 2013, opened and tabulated according to law, and the following bid was received complying with the advertisement:
 
Lametti & Sons, Inc.
$369,700.00
 
AND WHEREAS, the bid is substantially higher than the engineer's estimate for the project.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      The sole bid is hereby rejected, and the City Clerk is hereby authorized and directed to return forthwith the bid bond submitted by the bidder.  
 
PASSED by the City Council of the City of Blaine this 6th day June, 2013.