Project No. 11-16 includes asphalt pavement replacement, gravel shouldering, storm drainage improvements, culvert replacements and cleaning, traffic control signage, and appurtenant construction on Davenport Street from 93rd Lane to 91st Avenue and Isanti Street from 93rd Lane to Radisson Road.
The estimated total cost of the project is as follows:
Construction Costs
. |
$397,605.50 |
Engineering Costs
|
$ 94,551.52 |
Interest
... |
$ 10,558.16 |
Administration, Assessing, Other
... |
$ 24,746.08 |
Total
|
$527,461.26 |
The total project cost indicated in the Feasibility Report was $631,500.00.
The Assessment Roll has been prepared consistent with the Feasibility Report. Of the total cost, the amount to be assessed is $232,711.75.
Pavement Management Program Funds will contribute $294,749.51.
Recommendation
By motion, approve the resolution.
Body
WHEREAS, pursuant to Resolution No.13-149 passed by the Blaine City Council on September 5, 2013 the City Manager was directed to prepare a proposed assessment of the cost for asphalt pavement replacement, gravel shouldering, storm drainage improvements, culvert replacements and cleaning, traffic control signage, and appurtenant construction in the following described area:
Davenport Street from 93rd Lane to 91st Avenue
Isanti Street from 93rd Lane to Radisson Road
AND WHEREAS, the City Manager has notified the City Council that such proposed assessment has been completed and filed in his office for public inspection.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
1. A hearing shall be held on the 3rd day of October, 2013, in the Council Chambers at Blaine City Hall at 8:00 PM, or as near that time as possible, to pass upon such proposed assessment at such time and place all persons owning property affected by such improvement will be given an opportunity to be heard with reference to such assessment.
2. The City Manager shall give published and mailed notice of such hearing as required by law.
PASSED by the City Council of the City of Blaine this 5th day of September, 2013.