File #: RES 16-106    Version: 1 Name: Accept Bid for Reconstruct of Hastings St
Type: Resolution Status: Passed
File created: 6/16/2016 In control: City Council
On agenda: 6/16/2016 Final action: 6/16/2016
Title: ACCEPT BID FROM S. R. WEIDEMA, INC. IN THE AMOUNT OF $659,947.75 FOR THE RECONSTRUCTION OF HASTINGS STREET FROM 85TH AVENUE TO THE CUL-DE-SAC, IMPROVEMENT PROJECT NO. 15-22
Sponsors: Jean Keely
Attachments: 1. Hastings Street Location Map

ADMINISTRATION - Jean M. Keely, City Engineer

 

Title

ACCEPT BID FROM S. R. WEIDEMA, INC. IN THE AMOUNT OF $659,947.75 FOR THE RECONSTRUCTION OF HASTINGS STREET FROM 85TH AVENUE TO THE CUL-DE-SAC, IMPROVEMENT PROJECT NO. 15-22

 

Background

Bids were received at 10:15 AM, June 7, 2016, for Project No. 15-22.  A total of 10 bids were received ranging from $659,947.75 to $883,625.00.  The Engineer’s estimate for construction and the three lowest bidders are as follows:

 

Engineer’s Estimate - Construction Cost

$737,200.00

S. R. Weidema, Inc.

$659,947.75

Dresel Contracting, Inc.

$672,116.04

Geislinger and Sons, Inc.

$689,506.75

 

Bids have been checked and tabulated, and it has been determined that S. R. Weidema, Inc. of Maple Grove, Minnesota is the lowest bidder.  The Engineering Department has worked with S. R. Weidema, Inc. on previous contracts.  Staff recommends the low bid be accepted and a contract entered into with S. R. Weidema, Inc. 

 

City Council is also asked to approve a 10% contingency to bring the total project budget to $725,942.00.  The funding source for this project is assessments and the City Pavement Management Program Fund, and there are sufficient funds to cover these costs.

 

Recommendation

By motion, adopt the resolution.

 

Body

WHEREAS, pursuant to advertisement for bids for Improvement Project No. 15-22, said bids were received on June 7, 2016, opened and tabulated according to law, and the following three lowest bids were received complying with the advertisement:

 

S. R. Weidema, Inc.

$659,947.75

Dresel Contracting, Inc.

$672,116.04

Geislinger and Sons, Inc.

$689,506.75

 

AND WHEREAS, S. R. Weidema, Inc. of Maple Grove, Minnesota is the lowest responsible bidder.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The Mayor and City Manager are hereby authorized and directed to enter into a contract with S. R. Weidema, Inc. for the designated improvements in the amount of $659,947.75.

 

2.                     A 10% contingency is hereby approved to bring the total project budget to $725,942.00 and the Public Services Manager is hereby authorized to sign all change orders up to the authorized project budget amount.

 

3.                     The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bonds submitted with their bids, except the three lowest bidders.  When a contract is duly executed, the bid bonds of the two remaining unsuccessful bidders will be returned.  The bid bond of the successful bidder will be retained until the performance and payment bonds have been executed and approved, after which the bid bond will be returned.

 

PASSED by the City Council of the City of Blaine this 16th day of June, 2016.