Blaine logo
File #: MO 14-097    Version: 1 Name: Additional Engineering Services for Lift Station 12 & 13 - Improvement Project 13-10
Type: Motion Status: Passed
File created: 6/19/2014 In control: City Council
On agenda: 6/19/2014 Final action: 6/19/2014
Title: ACCEPT QUOTE FROM BARR ENGINEERING CO. IN THE AMOUNT OF $13,100 FOR ADDITIONAL ENGINEERING SERVICES FOR LIFT STATIONS NO. 12 & 13 IMPROVEMENT PROJECT NO. 13-10
Sponsors: Jean Keely
Attachments: 1. Barr Quote, 2. TKDA Quote
ADMINISTRATION - Jean M. Keely, City Engineer
 
Title
ACCEPT QUOTE FROM BARR ENGINEERING CO. IN THE AMOUNT OF $13,100 FOR ADDITIONAL ENGINEERING SERVICES FOR LIFT STATIONS NO. 12 & 13
IMPROVEMENT PROJECT NO. 13-10
 
Background
The Engineering Department has requested and received proposals from TKDA and Barr Engineering for design and construction services of electrical control panels for Lift Stations No. 12 and 13.  New pumps and generators for both lift stations have already been authorized by the City Council.  The proposal from TKDA is estimated at $14,550.  The proposal from Barr Engineering is estimated at $13,100.  Plans and specifications will be prepared and the project bid this summer for fall 2014 work.
 
 
 
Two quotes were received:
 
Barr Engineering Co.  …………………………………… $13,100
TKDA …………………………………………………… $14,550
 
Quotes have been checked and tabulated and Barr Engineering Co. submitted the lowest responsible quote.  The Engineering Department has worked previously with Barr Engineering Co. and recommends that the City Council accept the quote from Barr Engineering Co. to perform the work.  
 
Recommendation
By motion, authorize City Manager to accept the quote from Barr Engineering Co. in the amount of $13,100.