File #: RES 13-159    Version: 2 Name: Call for Hearing, Project 13-01
Type: Resolution Status: Passed
File created: 9/19/2013 In control: City Council
On agenda: Final action: 9/19/2013
Title: CALL FOR HEARING ON PROPOSED ASSESSMENT FOR PAVEMENT MANAGEMENT PROGRAM 2013 BITUMINOUS OVERLAY IMPROVEMENT PROJECT NO. 13-01
Sponsors: Stefan Higgins, Jean Keely
Attachments: 1. 13-01ProposedAssessment Roll.pdf, 2. Location Map.pdf
Related files: RES 13-176
ITEM:         12.3         ADMINISTRATION - Robert Therres, Public Services Manager
 
Title
CALL FOR HEARING ON PROPOSED ASSESSMENT FOR
PAVEMENT MANAGEMENT PROGRAM
2013 BITUMINOUS OVERLAY
IMPROVEMENT PROJECT NO. 13-01
 
Background
Project No. 13-01 includes a 1½ inch bituminous overlay, edge milling, spot curb replacement, and appurtenant construction.
 
The estimated total cost of the project is as follows:
 
Construction Costs………………….
$756,275.76
Engineering Costs…………………
$  36,594.39
Interest……………………………...
$    1,741.09
Administration, Assessing, Other…...
$  46,265.62
Total…………………………………
$840,876.86
 
The total project cost indicated in the Feasibility Report was $1,157,255.00.
 
The Assessment Roll has been prepared consistent with the Feasibility Report.  Of the total cost, the amount to be assessed is $403,002.50. The Pavement Management Program Funds will contribute $437,874.36.
 
Recommendation
By motion, approve the resolution.
 
Body
WHEREAS, pursuant to Resolution No. 13-158 passed by the Blaine City Council on September 19, 2013 the City Manager was directed to prepare a proposed assessment of the cost for a 1½ inch bituminous overlay, edge milling, spot curb replacement, and appurtenant construction in the following described area:
 
Baltimore St from 129th Ave to 132nd Ave
131st Ave from west of Baltimore St to Hastings St
Buchanan Cir from 126th Ave to cul-de-sac
126th Ave from Buchanan Cir to Ulysses St
Hastings St from 124th Ln to 125th Ave
124th Ln from west of Hastings St to Old Radisson Rd
Isanti Ct from 124th Ln to cul-de-sac
Xylite St from Rice Creek Pkwy to 93rd Ave
3rd St from 118th Ave to 120th Ln (including cul-de-sacs)
7th St from 118th Ave to north of 120th Ln
Terrace Rd from Washington St to 120th Ln
Washington St from 119th Ave to 120th Ln
Jefferson St from 119th Ave to north of 120th Ln
118th Ave from University Ave to Jefferson St
119th Ave from 7th St to Jefferson St
119th Cir from 3rd St to cul-de-sac
120th Ln from University Ave to cul-de-sac
120th Ln from 7th St to Jefferson St
Able St from 99th Ave to north of 99th Ln
99th Cir from Polk St to cul-de-sac
99th Ln from Able St to Polk St
102nd Cir from Tyler St to cul-de-sac
5th St from 91st Ln to 94th Ave
6th St from 93rd Ave to 94th Ave
7th St from 89th Ave to 91st Ave
7th St from 91st Ave to 93rd Ave
Terrace Rd from 7th St to 91st Ave
Terrace Rd from 91st Ave to 93rd Ave
Washington St from 89th Ln to Jefferson St
Washington St from 91st Ave to 93rd Ave
Jefferson St from 89th Ave to 93rd Ave
89th Ln from Washington St to Jefferson St
91st Ave from University Ave to Jefferson St
91st Ln from University Ave to 91st Ave
92nd Ave from 5th St to 7th St
93rd Ave from 5th St to Jefferson St
94th Ave from 5th St to 6th St
Van Buren Ct from 117th Ave to cul-de-sac
 
AND WHEREAS, the City Manager has notified the City Council that such proposed assessment has been completed and filed in his office for public inspection.
 
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
 
1.      A hearing shall be held on the 17th day of October, 2013, in the Council Chambers at Blaine City Hall at 8:00 PM, or as near that time as possible, to pass upon such proposed assessment at such time and place all persons owning property affected by such improvement will be given an opportunity to be heard with reference to such assessment.
 
2.      The City Manager shall give published and mailed notice of such hearing as required by law.
 
PASSED by the City Council of the City of Blaine this 19th day of September, 2013.