ADMINISTRATION - Jean M. Keely, City Engineer
Title
RECEIVE FEASIBILITY REPORT AND ORDER PUBLIC HEARING FOR THE PAVEMENT MANAGEMENT PROGRAM - 2015 BITUMINOUS OVERLAY, IMPROVEMENT PROJECT NO. 15-01
Background
The proposed improvements include a 1½ inch bituminous overlay, full width and edge milling, spot curb replacement and appurtenant construction on various city streets. The estimated total cost of the project is $426,200.00 with $127,197.26 proposed to be assessed over a five year period. The proposed assessment rate is a flat rate of $584.00 per residential lot unit or $11.69 per front foot for parcels zoned commercial/industrial and multi-family residential. The remaining portion of $299,002.74 is proposed to be paid from the City's Pavement Management Program funds. The project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.
Schedule of Actions
01/22/15 |
Initiate Project and Order Preparation of Feasibility Report |
02/19/15 |
Receive Feasibility Report and Order Public Hearing |
03/03/15 |
Hold Public Information Meeting |
03/19/15 |
Hold Public Hearing, Order Improvement, and |
|
Order Preparation of Plans and Specifications |
03/19/15 |
Approve Plans and Specifications and Order |
|
Advertisement for Bids |
04/21/15 |
Open Bids |
05/07/15 |
Accept Bid |
06-09/2015 |
Construct Improvements |
09/2015 |
Assess Improvements |
2016 |
First Assessment Payment Due with Real Estate Taxes |
Recommendation
By motion, adopt the resolution.
Body
WHEREAS, pursuant to Resolution No. 15-012 adopted on the 22nd day of January, 2015, by the Blaine City Council, a report has been prepared by the City of Blaine, Engineering Department, with reference to the Pavement Management Program -2015 Bituminous Overlay of various city streets, and this report received by the Council on the 19th day of February, 2015.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:
1. The Council will consider the improvement in accordance with the report finding the improvement necessary, cost-effective, and feasible and resulting in a benefit to the properties proposed to be assessed, and will consider the assessment of benefiting property for all or a portion of the cost of the improvement pursuant to the Minnesota Statutes, Chapter 429, at an estimated total cost of the improvement of $426,200.00.
2. A Public Hearing shall be held on such proposed improvement on the 19th day of March, 2015, at 8:00 PM in the Council Chambers of City Hall, and the City Clerk shall give mailed and published notice of such hearing and improvement as required by law.
PASSED by the City Council of the City of Blaine this 19th day of February, 2015.