ADMINISTRATION- Dan Schluender, City Engineer
Title
APPROVE CHANGE ORDER NO. 1 IN THE AMOUNT OF $140,603.78 FOR THE CLOVER LEAF PARKWAY AREA STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT NO. 18-18
Background
On May 20, 2019, a contract was awarded to Park Construction Company in the amount of $1,739,483.85 for the Clover Leaf Parkway Area Street Reconstructions.
During the project design and bidding phase it was not yet determined what the final layout of Central Avenue in Aquatore Park would be. As a result, reconstruction of only the northern 500 feet of Central Avenue was included in the construction plans. With the completion of the Mary Ann Young Center plans and draft Master Parks Plan, it is now proposed to reconstruct an additional 750 feet of Central Avenue with the Clover Leaf Parkway Area Street Reconstructions Project.
Change Order No. 1in the amount of $140,603.78 is for the reconstruction of this additional 750 feet of roadway on the south end of Central Avenue in Aquatore Park.
Recommendation
By motion, approve Change Order No. 1 to the contract for Improvement Project No 18-18 in the amount of $140,603.78, amending the total contract amount to $1,880,087.63 and authorizing the Public Services Manager to sign said Change Order No. 1.