Workshop Item Dan Schluender, City Engineer
Title
Title
99th Avenue and Baltimore Street Intersection Improvements
Project Update
end
Background
On February 23, Council authorized a contract for design services to improve the intersection of 99th Avenue and Baltimore Street. Since that time staff has worked with our consultant WSB to review the intersection and create a roundabout that will best handle the current traffic conditions and those that will be present in the future upgrades to TH 65/99th Avenue intersection. The attached concept layout shows the configuration of what the roundabout will look like and how it will fit into the corridor. The design team continues to coordinate the project with several agencies including Federal Highway Administration, Minnesota Department of Transportation, Metropolitan Airport Commission along with any agency that will need to approve the plan for the federal project process.
The current concept layout is nearing the 30% design plan and is being evaluated for impacts to wetlands, right-of-way, geotechnical, and traffic staging.
The project schedule is as follows,
30% Plans June/July 2022
60% Plans Sept./Oct. 2022
95% Plans Dec. ‘22/Jan. 2023
Final Approvals March/April 2023
Construction May/June 2023
Please note that the completion of each design plan stages, all agencies are given an opportunity to review and comment.
Staff Recommendation
This item is an informational update. No Council action is needed.
Attachment List
Concept Layout