Legislation Details

File #: RES 22-060    Version: 1 Name: Declare Cost to be Assessed-Project 21-06
Type: Resolution Status: Passed
File created: 4/18/2022 In control: City Council
On agenda: 4/18/2022 Final action: 4/18/2022
Title: Declare Cost to be Assessed, Order Preparation and Call for Hearing on Proposed Assessment for 2021 Street Reconstructions, Improvement Project No. 21-06
Sponsors: Dan Schluender
Attachments: 1. Project Location Map, 2. Assessable Parcels Maps, 3. 21-06 Final Assessment Roll

Consent Agenda- Dan Schluender, City Engineer

 

Title

 

Declare Cost to be Assessed, Order Preparation and Call for Hearing on Proposed Assessment for 2021 Street Reconstructions, Improvement Project No. 21-06

 

 

Executive Summary

Improvement Project No. 21-06 was ordered by the City Council on February 17, 2021 with Resolution 21-021.  A construction contract was awarded to Park Construction Company by the City Council on June 7, 2021 with Resolution No. 21-127 and construction was completed in the fall of 2021.

 

Background

Improvement Project No. 21-06 included the following project areas:

 

• Club West Parkway NE from 109th Avenue NE to Cloud Drive NE

• 93rd Lane Extension from to approximately 350-feet east of Anoka County-Blaine

  Airport Gate A to 85th Avenue NE

• 100th Court NE from Flanders Court NE to cul-de-sac

• Flanders Court NE from Radisson Road NE to 100th Court NE

• 105th Lane NE from National Street NE to Sunset Avenue

 

The total cost of the project is as follows:

 

Construction Costs………………….

$3,228,846.91

Engineering Costs…………………

$   509,289.76

Interest……………………………...

$     12,382.15

Administration, Assessing, Other…...

$   209,576.02

Total…………………………………

$3,960,094.84

 

The total project cost indicated in the Feasibility Report was $5,519,260.00.

 

The Assessment Roll has been prepared consistent with the Feasibility Report.

Of the total cost, the amount to be assessed is $752,398.15. The Public Utility Funds will contribute $153,407.57 for water and sanitary sewer improvements, Pavement Management Program funds will contribute $2,054,289.12 and MSAS will contribute $1,000,000.00. 

 

Strategic Plan Relationship

The 2021 Street Reconstructions project aligns with the City’s strategic plan goal of well-maintained infrastructure by providing high-quality street surfaces.

 

Board/Commission Review

Not required

 

Financial Impact

N/A

 

Public Outreach/Input

The project itself and the assessment process has complied with all public notification requirements pursuant to MN Statutes, Chapter 429.

 

Staff Recommendation

By motion, adopt the resolution.

 

Attachment List

Attached to this item are a project location map, assessable parcels map and the proposed final assessment roll.

 

 

Body

WHEREAS, a contract was entered into for bituminous pavement replacement with spot concrete curb and gutter repair/replacement, storm sewer drainage improvements, sanitary sewer improvements, traffic control signage, and appurtenant construction in the following described areas:

 

• Club West Parkway NE from 109th Avenue NE to Cloud Drive NE

• 93rd Lane Extension from to approximately 350-feet east of Anoka County-Blaine

  Airport Gate A to 85th Avenue NE

• 100th Court NE from Flanders Court NE to cul-de-sac

• Flanders Court NE from Radisson Road NE to 100th Court NE

• 105th Lane NE from National Street NE to Sunset Avenue

 

AND WHEREAS, the construction cost for such improvement is $3,228,846.91 and the expenses incurred in the making of said improvements amount to be $731,247.93 making the total cost $3,960,094.84.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     The total cost of such improvement is hereby declared to be $3,960,094.84.

 

2.                     The amount to be assessed is hereby declared to be $752,398.15.  The Public Utility Funds will contribute $153,407.57 for water and sanitary sewer improvements, Pavement Management Program funds will contribute $2,054,289.12 and MSAS will contribute $1,000,000.00. 

 

3.                     Assessments shall be payable in annual installments extending over a period of fifteen (15) years. The first of the installments to be payable on or before the first Monday in January 2023, and shall bear interest at the rate of 3.5% per annum from the date of the adoption of the assessment resolution.

 

4.                     The City Clerk, with the assistance of the City Engineer, shall forthwith calculate the proper amount to be specially assessed for such improvement against every assessable lot, piece, or parcel of land within the district affected without regard to cash valuation, as provided by law, and she shall file a copy of such proposed assessment in her office for public inspection.

 

5.                     The City Clerk has notified the City Council that such proposed assessment has been completed and filed in her office for public inspection.

 

6.                     A hearing shall be held on the 16th day of May, 2022, in the Council Chambers at the Blaine City Hall at 7:30 PM, or as near that time as possible, to pass upon the proposed assessment at such time and place all persons owning property affected by such improvement will be given an opportunity to be heard with reference to such assessment.

 

7.                     The City Clerk shall give published and mailed notice of such hearing as required by law.

 

PASSED by the City Council of the City of Blaine this 18th day of April, 2022.