Legislation Details

File #: RES 22-031    Version: 1 Name: 89th & Davenport Area St Reconstruction PH / Order P&S, I/P 22-05
Type: Resolution Status: Passed
File created: 3/7/2022 In control: City Council
On agenda: 3/7/2022 Final action: 3/7/2022
Title: Order Improvement and Order Preparation of Plans and Specifications for the 89th Avenue and Davenport Street Area Reconstructions, Improvement Project No. 22-05
Sponsors: Dan Schluender
Attachments: 1. Feasibility Report -89th & Davenport Final, 2. 89th Ave-Davenport St Area Location Map

Public Hearing - Dan Schluender, City Engineer

 

Title

Order Improvement and Order Preparation of Plans and Specifications for the 89th Avenue and Davenport Street Area Reconstructions, Improvement Project No. 22-05

 

Background

Notice for this hearing has been published and mailed. An open house for affected property owners was held on February 28, 2020. 

The proposed project will reconstruct the following streets:

 

•                     Baltimore Street from 85th Avenue to 89th Avenue

•                     Davenport Street from 85th Avenue to 89th Avenue

•                     89th Avenue from Central Avenue (Trunk Highway 65) to Davenport Street

•                     87th Avenue from Central Avenue (Trunk Highway 65) to Hastings Street

•                     Eldorado Street from 85th Avenue to 87th Avenue

•                     Goodhue Street from 85th Avenue to 87th Avenue

•                     Goodhue Street from 87th Avenue to northerly dead end

 

In addition, the project consists of a mill and overlay of the following Streets:

 

•                     Jenkins Court from 85th Avenue to the cul de sac

•                     86th Lane from Hastings Street to the cul de sac

 

The project area consists of city streets with rural sections and no curb and gutter, except for Jenkins Court and 86th Lane which do have concrete curb and gutter. The proposed improvements for the streets receiving a reconstruction include installing new concrete curb and gutter, aggregate base and bituminous pavement, storm sewer improvements, replacement of hydrants, repair/replacement of certain water main valves, traffic control signage replacement, and appurtenant construction.  The proposed improvements for streets receiving a mill and overlay include spot curb replacement and a 1-1/2 inch depth mill and overlay.

 

In addition to the street improvements, the proposed project also includes the reconstruction of Lift Station No. 1 and the force main associated with this lift station.

The estimated cost of these proposed improvements is $7,856,595 with $1,237,211 to be assessed to the benefitting properties over a 15-year period for streets being reconstructed and a 5-year period for streets receiving a mill and overlay.  Replacement of existing sanitary sewer castings/rings, hydrants, select valves and curb stops and reconstruction of Lift Station 1 and forcemain at an estimated cost of $2,979,855 is proposed to be paid for by City Public Utility Funds. The remaining portion of $3,639,529 is proposed to be paid from the City’s Pavement Management Program Funds. 

 

The proposed project is necessary, cost-effective, and feasible and will result in a benefit to the properties proposed to be assessed.

 

Schedule of Actions

09/20/2020

Initiate Project and Order Preparation of Feasibility Report

02/23/2022

Receive Feasibility Report and Order Public Hearing

02/28/2022

Public Information Meeting

03/07/2022

Hold Public Hearing, Order Improvement, and Order  Preparation of Plans and Specifications

04/04/2022

Approve Plans and Specification and Order Advertisement for Bids

05/03/2022

Open Bids

05/16/2022

Accept Bid

06/22-10/22

Construction of Improvements

02/2023

Assess Improvements

2024

First Assessment Payment Due with Real Estate Taxes

 

 

 

Recommendation

Hold Public Hearing and, by motion, adopt the resolution.

 

Body

WHEREAS, Resolution No. 22-024 the Blaine City Council, adopted on the 23rd day of February, 2022, ordered a public hearing on the proposed project; and

 

WHEREAS, the required notices were published and mailed to benefitting property owners, and the public hearing was held on the 7th day March, 2022, at which time all persons desiring to be heard were given an opportunity to be heard.

 

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Blaine as follows:

 

1.                     Such improvements are hereby ordered as proposed in the Feasibility Report, which was accepted by Resolution No. 22-024 adopted on the 23rd day of February, 2022.

 

2.                     The City Engineer is hereby designated as the Engineer for this improvement and is directed to prepare plans and specifications for the making of this improvement.

 

3.                     The City Council declares its official intent to reimburse itself for the costs of the improvement from the proceeds of tax exempt bonds.

 

PASSED by the City Council of the City of Blaine this 7th day of March, 2022.