File #: MO 22-031    Version: 1 Name: Approve Contract Amendment to TH65 Environmental Review
Type: Motion Status: Passed
File created: 2/7/2022 In control: City Council
On agenda: 2/7/2022 Final action: 2/7/2022
Title: Approve a Contract Amendment with TKDA for Professional Engineering Services toward the TH 65 Access Improvements, Project No. 21-01
Sponsors: Jon Haukaas
Attachments: 1. TH 65 Phase1A-Scope of Work Amended, 2. TH65_FeeEstimate-Phase1A-Amendment

Administration - Jon Haukaas, Public Works Director

 

Title

title

Approve a Contract Amendment with TKDA for Professional Engineering Services toward the TH 65 Access Improvements, Project No. 21-01

end

 

Executive Summary

Staff requests Council approval to amend the contract with TKDA for professional engineering services to expand scope of the Phase 1 contract for the initial stage of environmental review and documentation of the TH 65 Access Improvements, Project Number 21-01. 

 

Background

The City Council approved a contract with TKDA on April 19, 2021 to perform the environmental review and documentation of the TH 65 Access Improvements as the initial phase toward these projects.  This Phase 1 contract addresses the environmental review of the TH 65 Section 2 corridor.  The final product of this phase is the selection of a Preferred Alternative. 

 

Additional options were determined during project development that better addressed the goals of the project and therefore required a deeper level of analysis.  Specifically;

•                     Three (3) additional Project Management Team (PMT) meetings.  The PMT is comprised of representatives of FHWA, multiple MnDOT divisions, Anoka County, City of Blaine, and multiple consultant teams.

•                     Additional coordination meetings between the agencies and property owners (2) and with the neighborhood (1) for outreach.

•                     Concept development, design refinement, constructability, and cost estimates for Alternative 1A determined after the original contract scope was initiated.

•                     Additional traffic analysis and subsequent refinement of lane/intersection geometry for Alternative 1A.

 

 

City Council is asked to approve a contract amendment in the amount of $246,792 to cover the expanded Scope of Work. 

 

Strategic Plan Relationship

Improvements to TH65 are identified as a priority in the City Strategic Plan.  Additionally, this project is part of the City’s strategic initiative to have a well-maintained infrastructure by improving safety and reducing congestion of the main corridor through Blaine. 

 

Board/Commission Review

Not required.

 

Financial Impact

With approval of this amendment, the budget for this phase is as follows:

                     Initial contract                                          $    976,825

                     Approved Contingency                     $      96,675

                     Contract Amendment                     $    246,792

                                                                                                         $ 1,320,292

 

These expenditures will be reimbursed by the $1.5 million 2020 grant from the state legislature to Anoka County for the environmental review of the entire section 2 corridor. On February 1, 2021 the City and County entered into a Joint Powers Agreement for the use of these funds.

 

Public Outreach/Input

None required.

 

Staff Recommendation

By motion, approve the amendment the contract with TKDA for additional services in the total not to exceed amount of $1,320,292, an increase of $246,792, and authorize the City Manager to sign the amendment to the contract.

 

Attachment List

•                     TH65 Phase 1A - Scope of Work - revised

•                     TH65 Fee Estimate Phase 1A Amendment