Park Board Item - Jerome Krieger, Senior Parks and Recreation Manager
Title
Title
Park Updates
end
Background
Aquatore Shelter Replacements - The shelters are scheduled to arrive on site by December 6th. We have a substantial completion date of December 20th for the shelters.
Sunrise Trail and Happy Acres projects are still waiting for final approval from Coon Creek watershed.
Monument signs for Lexington Athletic Complex and Blaine Wetland Sanctuary started construction this week.
We are moving forward with WSB and Associates and HCM Architects for the Blaine Wetland Sanctuary Shelter and Restroom facility project. A kick - off meeting will take place in December.
Band shell update - We received 5 quotes for the Architectural and Design Services. ISG Incorporated from Mankato, Minnesota was the low quote. I will be presenting this to council on December 6th.
Trail Pavement Management - Braun Intertec was able to do a partial assessment of some of the trails and parking lots this fall. They are tabulating the scores and will be providing us the assessment of those parks by January. They will continue with the other parks and trails in the spring.
There will not be a December Park Board meeting.
Staff Recommendation
Informational