Legislation Details

File #: RES 21-030    Version: 1 Name: Final Plat - Woods at Quail Creek 5th (21-0010)
Type: Resolution Status: Passed
File created: 3/1/2021 In control: City Council
On agenda: 3/1/2021 Final action: 3/1/2021
Title: Granting Final Plat Approval to Subdivide Approximately 12.75 Aces into 19 Single Family Lots to be Known as Woods at Quail Creek 5th Addition, Located at the North End of Xylite Street NE. Newmark Homes Inc. (Case File No. 21-0010/LSJ)
Sponsors: Lori Johnson
Attachments: 1. Attachments

Development Business - Lori Johnson, City Planner

 

Title

Granting Final Plat Approval to Subdivide Approximately 12.75 Aces into 19 Single Family Lots to be Known as Woods at Quail Creek 5th Addition, Located at the North End of Xylite Street NE. Newmark Homes Inc. (Case File No. 21-0010/LSJ)

 

Executive Summary

This final plat is consistent with the approved preliminary plat of Woods at Quail Creek 5th Addition, which was approved in 2020. The final plat includes 19 single family lots.

 

Schedule of Actions

Planning Commission (Public Hearing)

07/14/20

City Council (Preliminary Plat)

08/17/20

City Council (Final Plat)

03/01/21

 

Background

Staff report prepared by Lori Johnson, City Planner

 

The applicant, MG Main Street Properties, is proposing to final plat the 12.75 acres just north of the Woods at Quail Creek 4th Addition into 19 single family lots. The plat also contains the extension of Xylite Street north to where it meets 129th Lane NE at the intersection of Alamo Ct NE and then continues on to the Springbrook Addition.

 

Outlot A is for storm drainage purposes and wetlands.

 

Park dedication will be required for the 19 lots in this plat in the amount of $4,449 per lot for a total of $84,531. This amount is due prior to release of final plat mylars for recording purposes.

 

Sidewalks will be constructed along the east side of Xylite Street and the north side of 129th Lane.

 

Trunk sanitary sewer area charges become due with platting for upland acreage. The 2021 rate for Sanitary Sewer District 6-5 is $6,338.00 per acre and will apply to all upland acreage if platted in 2021.

 

There will be significant tree loss as the site is heavily wooded and approximately 8 acres are being disturbed during grading activity. The City’s Tree Preservation ordinance requires replacement for a portion of those trees at the rate of eight (8) trees per acre, which would result in 64 replacement trees. To replace these trees, the developer will be required to plant three (3) trees per lot (57 trees). The developer will also need to submit a landscape plan prior to grading approval that indicates where the remaining seven (7) replacement trees will be located.

 

Appropriate signage to be installed at all property corners around the storm water management features at the edge of single family lots.

 

Developer will be required to obtain a Coon Creek Watershed permit prior to commencement of any site work.

 

Strategic Plan Relationship

This final plat meets the goal of maintaining current residential growth in the strategic plan.

 

Board/Commission Review

The Planning Commission voted unanimously to approve the preliminary plat. The Planning Commission does not review the final plat.

 

Financial Impact

Not applicable.

 

Public Outreach/Input

No public notice is required for final plat approval. When a public hearing on this item was held in July of 2020, the standard notice was sent to all property owners within 350 feet of the property lines of this plat.

 

Staff Recommendation

By motion, approve the Resolution.

 

Attachment List

Zoning and Location Map

Final Plat

 

Body

                     WHEREAS, an application has been filed by Newmark Homes Inc as subdivision Case No. 21-0010; and

 

                     WHEREAS, said case involves the division of land in Anoka County, Minnesota, described as follows:

 

THAT PART OF OUTLOT D, QUAIL CREEK 10TH ADDITION, ANOKA COUNTY, MINNESOTA, THAT LIES SOUTHEASTERLY OF THE FOLLOWING DESCRIBED LINE; COMMENCING AT THE SOUTHEAST CORNER OF SAID OUTLOT D; THENCE NORTH 88 DEGREES 18 MINUTES 58 SECONDS WEST, ALONG THE SOUTH LINE OF SAID OUTLOT D, 950.90 FEET TO THE POINT OF BEGINNING OF SAID LINE TO BE DESCRIBED; THENCE NORTH 20 DEGREES 40 MINUTES 31 SECONDS EAST 275.48 FEET; THENCE NORTH 21 DEGRESS 03 MINUTES 52 SECONDS EAST 359.40 FEET; THENCE NORTH 79 DEGREES 53 MINUTES 59 SECONDS EAST 731.83 FEET TO THE EAST LINE OF SAID OUTLOT D AND THERE TERMINATING.

 

                     WHEREAS, the Blaine City Council granted preliminary plat approval on August 17, 2020, subject to the stipulations as contained in Blaine City Council Resolution No. 20-114; and

 

                     WHEREAS, the applicant has submitted a final plat in general conformance with the approved preliminary plat.

 

                     NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Blaine that final plat approval for Woods at Quail Creek 5th Addition per Section 74-43 of the subdivision regulations is hereby granted subject to the following conditions:

 

1.                     All streets will follow the Anoka County street name grid system.

2.                     Developer installed improvements shall include construction of lateral sanitary sewer and water main with services, storm drainage improvements, storm water management and water quality treatment infrastructure, streets with concrete curb and gutter, 6 foot concrete sidewalks, streetlights, mailboxes, traffic control signs, street signs, and all appurtenant items.

3.                     Trunk sanitary sewer area charges become due with platting for upland acreage. The 2021 rate for Sanitary Sewer District 6-5 is $6,338.00 per upland acre.

4.                     Street and utility extensions are required to the edge of the plat for each connection to the adjacent parcel.

5.                     Standard utility and drainage easements must be dedicated along all lot lines and over areas of delineated wetlands, wetland mitigation, infiltration trenches, drainage swales, and storm water management ponds.

6.                     Hydrant locations must be reviewed and approved by the Fire Department.

7.                     The Developer is to provide access for inspection and maintenance of storm water management infrastructure. Restrictions will be placed on lot lines as needed to limit fences and landscaping to insure access.

8.                     Development requires a National Pollutant Discharge Elimination System (NPDES) Phase II General Storm Water Permit for Construction Activity (MN R100001) from Minnesota Pollution Control Agency (MPCA). A prerequisite to the MPCA permit application includes preparation of a site Storm Water Pollution Prevention Plan (SWPPP) for the development site.

9.                     Construction contract documents shall include a mass (rough) grading, erosion protection, sediment control, development, utilities, roadway, and storm drainage plan sheet(s). Supporting wetland delineation report, geotechnical investigation report, soil boring logs, and hydrology report shall be included in the submittal for city engineer review and approval. Plans and specifications must be approved by the City prior to start of construction.

10.                     Sidewalk improvements must be soil corrected to full depth. Driveway subgrades must be fully corrected or provide a geotechnical report designing an alternate section. Driveways not having fully corrected subgrades shall have an extended warranty to protect future property owners. The development contract shall set forth the length and details of the warranty.

11.                     The development plan shall indicate all structures will be protected from flooding.

12.                     A twenty-foot buffer strip shall be provided adjacent to wetland edges and shall be placed in an easement. All buildings will be provided a 30-foot setback from all wetland boundaries.

13.                     Appropriate signage to be installed at all property corners around the storm water management features and wetland boarders at the edge of single family lots.

14.                     CCWD permit is required prior to city approval of construction plans and specifications.

15.                     As-built surveys shall be required to verify structure elevations, custom grading requirements, and final lot grading elevations.

16.                     Building permits will not be issued for homes in the plat until city sanitary sewer and water, as part of the Developer Installed Improvements, have been installed and accepted by the City Engineering Department, and a paved street is available. Certificate of Occupancy will not be issued until all private utilities (electric, gas, etc.) are installed. Building permits and inspections may be withheld if satisfactory progress is not being made on the construction of Developer Installed Improvements.

17.                     The plat to meet the City’s Tree Preservation requirements by planting 64 replacement trees. To replace these trees, the developer will be required to plant three trees per lot (57 trees). The developer will also need to submit a landscape plan prior to grading approval that indicates where the remaining 7 replacement trees will be located.

18.                     Developer to require homeowner’s associations to be responsible for maintenance and upkeep of landscape or development signage improvements along and within the right-of-way except for typical individual lot boulevard sod and tree plantings.

19.                     Developer to install grouped mailboxes with design and locations approved by city and US Postal Service.

20.                     Developer shall explore water source for landscape irrigation systems installed throughout the development including the possible use of created ponds, existing wells, or new wells as source of water supply with a moisture sensor installed.

21.                     Water and sanitary sewer availability charges (WAC & SAC) become due with each building permit at the rate established at the time the building permit is issued.

22.                     Sidewalks will be constructed along the east side of Xylite Street and the north side of 129th Lane.

23.                     All development signage issued under a separate permit.

24.                     Execution and recording of a Development Agreement, which sets forth in greater detail the plat conditions and park development as well as other responsibilities for the development of this plat.

25.                     Park dedication will be required for the 19 lots in this plat in the amount of $4,449 per lot for a total of $84,531. This amount is due prior to release of final plat mylars for recording purposes.

26.                     The Mayor, City Clerk and City Manager are hereby authorized to execute any and all necessary documents, agreements and releases related to the approval, recording or administration of the Woods at Quail Creek 5th Addition plat.

 

PASSED by the City Council of the City of Blaine this 1st day of March, 2021.