File #: MO 22-181    Version: 1 Name: Authorize Change Order city hall remodel
Type: Motion Status: Agenda Ready
File created: 11/7/2022 In control: City Council
On agenda: 11/7/2022 Final action:
Title: Authorize Change Order for the City Hall Remodel Project
Sponsors: Michelle Wolfe
Attachments: 1. Change Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Consent  - Michelle Wolfe, City Manager

 

Title

Title

Authorize Change Order for the City Hall Remodel Project

end

 

Executive Summary

Council is requested to approve a change order for the City Hall remodel project. Project funding is available and this is a procedural request for approval and signature which is required with a change in contract cost.

 

Background

On March 15, 2021, Council award the bids and quotes for the City Hall/Police Department improvements. Construction began in April of 2021 and is now nearing completion. RJM Construction has presented the City with a change order in the amount of $56,373.10. The increase is primarily due to supply chain issues and material and labor cost increases.

 

Project funding is available and additional funds are not being requested.

 

Strategic Plan Relationship

Well-maintained infrastructure. Improvements made during the remodel will meet the needs of the community for the next 20 years.

 

Board/Commission Review

Not required.

 

Financial Impact

None

 

Staff Recommendation

By motion, approve the change order in the amount of $56,373.10.

 

Attachment List

Change Order